T1 - Delay causes in Kazakhstan’s construction projects and remedial measures
AU - Hossain, Md Aslam
AU - Raiymbekov, Dinmukhambet
AU - Nadeem, Abid
AU - Kim, Jong Ryeol
N1 - Funding Information:
The authors would like to express their heartfelt gratitude to the respondents who participated in the survey and interviews and provided valuable feedback for this research.
Publisher Copyright:
© 2019 Informa UK Limited, trading as Taylor & Francis Group.
PY - 2022
Y1 - 2022
N2 - Delay in construction projects is a major concern. Research was conducted to find the construction delay causes and mitigation measures. Literature reveals that different countries experience various causes of delays and significances of these causes are different based on project types. This study explores delay causes in Kazakhstan’s construction industry and analyzes their influence on different types of construction projects. Fifty-five delay causes relevant to construction projects in Kazakhstan have been identified through literature review and primary interviews with selected construction professionals. Afterwards, a comprehensive survey was conducted among the industry professionals. The survey results show that different delay causes have different importance based on the project types (industrial, residential, commercial, etc). Moreover, project parties (client, contractor and consultant) have different views on the delay causes. Accordingly, the study ranks delay causes based on project parties and project types and compares their correlations. Finally, recommendations for the most prominent delay causes have been provided. This study provides better understanding on delay causes and gives important guideline for stakeholders of Kazakhstani construction industry and other construction professionals in the world to control their projects. Similar studies can be conducted in other countries to identify causes and remedial measures for delays.
AB - Delay in construction projects is a major concern. Research was conducted to find the construction delay causes and mitigation measures. Literature reveals that different countries experience various causes of delays and significances of these causes are different based on project types. This study explores delay causes in Kazakhstan’s construction industry and analyzes their influence on different types of construction projects. Fifty-five delay causes relevant to construction projects in Kazakhstan have been identified through literature review and primary interviews with selected construction professionals. Afterwards, a comprehensive survey was conducted among the industry professionals. The survey results show that different delay causes have different importance based on the project types (industrial, residential, commercial, etc). Moreover, project parties (client, contractor and consultant) have different views on the delay causes. Accordingly, the study ranks delay causes based on project parties and project types and compares their correlations. Finally, recommendations for the most prominent delay causes have been provided. This study provides better understanding on delay causes and gives important guideline for stakeholders of Kazakhstani construction industry and other construction professionals in the world to control their projects. Similar studies can be conducted in other countries to identify causes and remedial measures for delays.
KW - Delay causes
KW - construction project types
KW - project parties
KW - remedial measures
UR - http://www.scopus.com/inward/record.url?scp=85079824309&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=85079824309&partnerID=8YFLogxK
U2 - https://doi.org/10.1080/15623599.2019.1647635
DO - https://doi.org/10.1080/15623599.2019.1647635
M3 - Article
AN - SCOPUS:85079824309
SN - 1562-3599
VL - 22
SP - 801
EP - 819
JO - International Journal of Construction Management
JF - International Journal of Construction Management
IS - 5
ER -