Investigation of wasteful activities using lean methodology: In perspective of kazakhstan's construction industry

Md Aslam Hossain, Assel Bissenova, Jong Kim

Research output: Contribution to journalArticle

Abstract

Like many other countries, the presence of wasteful activities is very common in Kazakhstan's construction industry. This severely affects the productivity of construction processes. Lean methodology maximizes the value of a process by minimizing wasteful or non-value adding (NVA) activities. This study aims to explore and quantify the impact NVA items on construction productivity. Several observations were made for construction processes in Astana, Kazakhstan to investigate and quantify various types of wasteful activities. Moreover, a survey was conducted to examine the general understanding of wasteful activities and Lean methods within the construction industry in Kazakhstan. In terms of wasteful activities, a similarity was found between the observed construction processes and survey results. Furthermore, apart from the commonly found seven types of wasteful activities, some other sources of waste, such as "preparation" and "break", were found from the observations. Finally, wasteful activities were mapped with commonly used Lean tools, as found in the literature, so that productivity can be improved by minimizing NVA activities. From the mapping and the survey results, value stream mapping (VSM) was found to be the most effective Lean tool, since it facilitates increased visualization.

Original languageEnglish
Article number113
JournalBuildings
Volume9
Issue number5
DOIs
Publication statusPublished - Jan 1 2019

Fingerprint

Construction industry
Productivity
Visualization

Keywords

  • Construction process
  • Lean methods
  • Non-value adding activities
  • Productivity improvement
  • Value adding activities

ASJC Scopus subject areas

  • Architecture
  • Civil and Structural Engineering
  • Building and Construction

Cite this

Investigation of wasteful activities using lean methodology : In perspective of kazakhstan's construction industry. / Hossain, Md Aslam; Bissenova, Assel; Kim, Jong.

In: Buildings, Vol. 9, No. 5, 113, 01.01.2019.

Research output: Contribution to journalArticle

@article{d23410a7e85441b78b9732c419e8d80f,
title = "Investigation of wasteful activities using lean methodology: In perspective of kazakhstan's construction industry",
abstract = "Like many other countries, the presence of wasteful activities is very common in Kazakhstan's construction industry. This severely affects the productivity of construction processes. Lean methodology maximizes the value of a process by minimizing wasteful or non-value adding (NVA) activities. This study aims to explore and quantify the impact NVA items on construction productivity. Several observations were made for construction processes in Astana, Kazakhstan to investigate and quantify various types of wasteful activities. Moreover, a survey was conducted to examine the general understanding of wasteful activities and Lean methods within the construction industry in Kazakhstan. In terms of wasteful activities, a similarity was found between the observed construction processes and survey results. Furthermore, apart from the commonly found seven types of wasteful activities, some other sources of waste, such as {"}preparation{"} and {"}break{"}, were found from the observations. Finally, wasteful activities were mapped with commonly used Lean tools, as found in the literature, so that productivity can be improved by minimizing NVA activities. From the mapping and the survey results, value stream mapping (VSM) was found to be the most effective Lean tool, since it facilitates increased visualization.",
keywords = "Construction process, Lean methods, Non-value adding activities, Productivity improvement, Value adding activities",
author = "Hossain, {Md Aslam} and Assel Bissenova and Jong Kim",
year = "2019",
month = "1",
day = "1",
doi = "10.3390/buildings9050113",
language = "English",
volume = "9",
journal = "Buildings",
issn = "2075-5309",
publisher = "Multidisciplinary Digital Publishing Institute (MDPI)",
number = "5",

}

TY - JOUR

T1 - Investigation of wasteful activities using lean methodology

T2 - In perspective of kazakhstan's construction industry

AU - Hossain, Md Aslam

AU - Bissenova, Assel

AU - Kim, Jong

PY - 2019/1/1

Y1 - 2019/1/1

N2 - Like many other countries, the presence of wasteful activities is very common in Kazakhstan's construction industry. This severely affects the productivity of construction processes. Lean methodology maximizes the value of a process by minimizing wasteful or non-value adding (NVA) activities. This study aims to explore and quantify the impact NVA items on construction productivity. Several observations were made for construction processes in Astana, Kazakhstan to investigate and quantify various types of wasteful activities. Moreover, a survey was conducted to examine the general understanding of wasteful activities and Lean methods within the construction industry in Kazakhstan. In terms of wasteful activities, a similarity was found between the observed construction processes and survey results. Furthermore, apart from the commonly found seven types of wasteful activities, some other sources of waste, such as "preparation" and "break", were found from the observations. Finally, wasteful activities were mapped with commonly used Lean tools, as found in the literature, so that productivity can be improved by minimizing NVA activities. From the mapping and the survey results, value stream mapping (VSM) was found to be the most effective Lean tool, since it facilitates increased visualization.

AB - Like many other countries, the presence of wasteful activities is very common in Kazakhstan's construction industry. This severely affects the productivity of construction processes. Lean methodology maximizes the value of a process by minimizing wasteful or non-value adding (NVA) activities. This study aims to explore and quantify the impact NVA items on construction productivity. Several observations were made for construction processes in Astana, Kazakhstan to investigate and quantify various types of wasteful activities. Moreover, a survey was conducted to examine the general understanding of wasteful activities and Lean methods within the construction industry in Kazakhstan. In terms of wasteful activities, a similarity was found between the observed construction processes and survey results. Furthermore, apart from the commonly found seven types of wasteful activities, some other sources of waste, such as "preparation" and "break", were found from the observations. Finally, wasteful activities were mapped with commonly used Lean tools, as found in the literature, so that productivity can be improved by minimizing NVA activities. From the mapping and the survey results, value stream mapping (VSM) was found to be the most effective Lean tool, since it facilitates increased visualization.

KW - Construction process

KW - Lean methods

KW - Non-value adding activities

KW - Productivity improvement

KW - Value adding activities

UR - http://www.scopus.com/inward/record.url?scp=85071691767&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=85071691767&partnerID=8YFLogxK

U2 - 10.3390/buildings9050113

DO - 10.3390/buildings9050113

M3 - Article

AN - SCOPUS:85071691767

VL - 9

JO - Buildings

JF - Buildings

SN - 2075-5309

IS - 5

M1 - 113

ER -