Optimising the long-term mine waste management and truck schedule in a largescale open pit mine

Yu Li, Erkan Topal, Salih Ramazan

Research output: Contribution to journalArticle

7 Citations (Scopus)

Abstract

A mine landform progression plan can provide a clear outlook of the entire mining operation. To produce such an output requires detailed placement schedule of the mined material, including the volume (or tonnage) and the allocated dumping location. However, current practices mainly focus on the ore production, over-simplifying the waste material scheduling. As a result, a rock dump is often treated as a single point in long-term planning, making it difficult to predict the progression pattern over the life of mine. Without such a guidance, it is almost impossible to carry out progressively rehabilitate of the waste rock dumps. The lack of detailed waste material dumping schedule could cause delay in development construction, i.e. tailing storage facility and Run of Mine-pad. Other downstream effect due to the over-simplification is an inaccurate estimation of required truck, which could have huge financial impact on the operation. In this paper, mixed integer programming models of different objective functions, i.e. maximise truck productivity by minimising the overall haulage distance, minimise required truck deviation between adjacent years, and a hybrid between the two objectives, are utilised to generate the long-term optimum rock placement schedules under the condition of satisfying sitespecific requirements. All three models are implemented in a large-scale open pit mine. The numerical solutions from the models form three different schedules of mined material placement, based on which, the yearly truck requirements are easily calculated and compared. The graphical results show the three corresponding landform progression patterns over the life of mine, providing the optimised long-term forecast of the operation.

Original languageEnglish
Pages (from-to)35-46
Number of pages12
JournalTransactions of the Institution of Mining and Metallurgy, Section A: Mining Technology
Volume125
Issue number1
DOIs
Publication statusPublished - 2016
Externally publishedYes

Fingerprint

open pit mine
mine waste
Waste management
Trucks
waste management
Landforms
landform
Rocks
rock
haulage
tailings
Tailings
Integer programming
Ores
productivity
Productivity
Scheduling
material
Planning
dumping

Keywords

  • Landform progression
  • Maximising truck productivity
  • Mixed integer programming
  • Truck scheduling
  • Waste dump scheduling and optimisation

ASJC Scopus subject areas

  • Geotechnical Engineering and Engineering Geology
  • Geology

Cite this

Optimising the long-term mine waste management and truck schedule in a largescale open pit mine. / Li, Yu; Topal, Erkan; Ramazan, Salih.

In: Transactions of the Institution of Mining and Metallurgy, Section A: Mining Technology, Vol. 125, No. 1, 2016, p. 35-46.

Research output: Contribution to journalArticle

@article{a6dfa55fa3c14a3c887034a6e16c5443,
title = "Optimising the long-term mine waste management and truck schedule in a largescale open pit mine",
abstract = "A mine landform progression plan can provide a clear outlook of the entire mining operation. To produce such an output requires detailed placement schedule of the mined material, including the volume (or tonnage) and the allocated dumping location. However, current practices mainly focus on the ore production, over-simplifying the waste material scheduling. As a result, a rock dump is often treated as a single point in long-term planning, making it difficult to predict the progression pattern over the life of mine. Without such a guidance, it is almost impossible to carry out progressively rehabilitate of the waste rock dumps. The lack of detailed waste material dumping schedule could cause delay in development construction, i.e. tailing storage facility and Run of Mine-pad. Other downstream effect due to the over-simplification is an inaccurate estimation of required truck, which could have huge financial impact on the operation. In this paper, mixed integer programming models of different objective functions, i.e. maximise truck productivity by minimising the overall haulage distance, minimise required truck deviation between adjacent years, and a hybrid between the two objectives, are utilised to generate the long-term optimum rock placement schedules under the condition of satisfying sitespecific requirements. All three models are implemented in a large-scale open pit mine. The numerical solutions from the models form three different schedules of mined material placement, based on which, the yearly truck requirements are easily calculated and compared. The graphical results show the three corresponding landform progression patterns over the life of mine, providing the optimised long-term forecast of the operation.",
keywords = "Landform progression, Maximising truck productivity, Mixed integer programming, Truck scheduling, Waste dump scheduling and optimisation",
author = "Yu Li and Erkan Topal and Salih Ramazan",
year = "2016",
doi = "10.1080/14749009.2015.1107343",
language = "English",
volume = "125",
pages = "35--46",
journal = "Transactions of the Institutions of Mining and Metallurgy, Section A: Mining Technology",
issn = "1474-9009",
publisher = "Maney Publishing",
number = "1",

}

TY - JOUR

T1 - Optimising the long-term mine waste management and truck schedule in a largescale open pit mine

AU - Li, Yu

AU - Topal, Erkan

AU - Ramazan, Salih

PY - 2016

Y1 - 2016

N2 - A mine landform progression plan can provide a clear outlook of the entire mining operation. To produce such an output requires detailed placement schedule of the mined material, including the volume (or tonnage) and the allocated dumping location. However, current practices mainly focus on the ore production, over-simplifying the waste material scheduling. As a result, a rock dump is often treated as a single point in long-term planning, making it difficult to predict the progression pattern over the life of mine. Without such a guidance, it is almost impossible to carry out progressively rehabilitate of the waste rock dumps. The lack of detailed waste material dumping schedule could cause delay in development construction, i.e. tailing storage facility and Run of Mine-pad. Other downstream effect due to the over-simplification is an inaccurate estimation of required truck, which could have huge financial impact on the operation. In this paper, mixed integer programming models of different objective functions, i.e. maximise truck productivity by minimising the overall haulage distance, minimise required truck deviation between adjacent years, and a hybrid between the two objectives, are utilised to generate the long-term optimum rock placement schedules under the condition of satisfying sitespecific requirements. All three models are implemented in a large-scale open pit mine. The numerical solutions from the models form three different schedules of mined material placement, based on which, the yearly truck requirements are easily calculated and compared. The graphical results show the three corresponding landform progression patterns over the life of mine, providing the optimised long-term forecast of the operation.

AB - A mine landform progression plan can provide a clear outlook of the entire mining operation. To produce such an output requires detailed placement schedule of the mined material, including the volume (or tonnage) and the allocated dumping location. However, current practices mainly focus on the ore production, over-simplifying the waste material scheduling. As a result, a rock dump is often treated as a single point in long-term planning, making it difficult to predict the progression pattern over the life of mine. Without such a guidance, it is almost impossible to carry out progressively rehabilitate of the waste rock dumps. The lack of detailed waste material dumping schedule could cause delay in development construction, i.e. tailing storage facility and Run of Mine-pad. Other downstream effect due to the over-simplification is an inaccurate estimation of required truck, which could have huge financial impact on the operation. In this paper, mixed integer programming models of different objective functions, i.e. maximise truck productivity by minimising the overall haulage distance, minimise required truck deviation between adjacent years, and a hybrid between the two objectives, are utilised to generate the long-term optimum rock placement schedules under the condition of satisfying sitespecific requirements. All three models are implemented in a large-scale open pit mine. The numerical solutions from the models form three different schedules of mined material placement, based on which, the yearly truck requirements are easily calculated and compared. The graphical results show the three corresponding landform progression patterns over the life of mine, providing the optimised long-term forecast of the operation.

KW - Landform progression

KW - Maximising truck productivity

KW - Mixed integer programming

KW - Truck scheduling

KW - Waste dump scheduling and optimisation

UR - http://www.scopus.com/inward/record.url?scp=84964866094&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84964866094&partnerID=8YFLogxK

U2 - 10.1080/14749009.2015.1107343

DO - 10.1080/14749009.2015.1107343

M3 - Article

AN - SCOPUS:84964866094

VL - 125

SP - 35

EP - 46

JO - Transactions of the Institutions of Mining and Metallurgy, Section A: Mining Technology

JF - Transactions of the Institutions of Mining and Metallurgy, Section A: Mining Technology

SN - 1474-9009

IS - 1

ER -