Real option in action

An example of flexible decision making at a mine operational level

Ajak Duany Ajak, Erkan Topal

Research output: Contribution to journalArticle

17 Citations (Scopus)

Abstract

Flexibility and operational adaptability are essential for long term corporate success and real option (RO) appears suitable for analysing risky projects. Nevertheless, its application in engineering design has been slow-moving compared to financial uses. Therefore, there is a compelling argument for using visual, intuitive and transparent models, such as the binomial decision tree, which has the potential to eliminate decision maker apprehension and improve RO use in engineering design and decision making. This paper reviews RO applications in mining projects and proposes a new methodology to explore technical applications of RO in mine design and decision making at the mine operational level. The research will investigate the suitability of using the RO method at the mine operational level where production decisions are made frequently, rather than organisational strategies that are reviewed after several years. The proposed approach is applied to a case study. This will demonstrate how RO can be used in designing multiple pits in multi-zone ore deposits to create a switching option between pits regarding changing ore grades and fluctuating commodity prices. The main rationale of this option involves deferring waste materials by switching mining activities from a high to low strip ratio pit. This creates a choice between using new RO thinking and the traditional methodology. The option is analysed using the binomial decision tree. The results summarised in this paper's conclusion reveal that the project's value increased considerably when flexibility was included in the mine design. These increases in project value were between eight to 15 per cent, depending on the number of flexible options incorporated into the design.

Original languageEnglish
Pages (from-to)109-120
Number of pages12
JournalResources Policy
Volume45
DOIs
Publication statusPublished - 2015
Externally publishedYes

Fingerprint

decision making
flexibility
engineering
methodology
commodity price
ore grade
commodity
decision maker
Values
ore deposit
Real options
Decision making
decision
project
Decision tree
Methodology
Engineering design

Keywords

  • Application of real option at mine operational level
  • Binomial model
  • Decision making
  • Flexible design
  • Risk
  • Switching option between pits
  • Uncertainty

ASJC Scopus subject areas

  • Economics and Econometrics
  • Management, Monitoring, Policy and Law
  • Law
  • Sociology and Political Science

Cite this

Real option in action : An example of flexible decision making at a mine operational level. / Ajak, Ajak Duany; Topal, Erkan.

In: Resources Policy, Vol. 45, 2015, p. 109-120.

Research output: Contribution to journalArticle

Ajak, Ajak Duany ; Topal, Erkan. / Real option in action : An example of flexible decision making at a mine operational level. In: Resources Policy. 2015 ; Vol. 45. pp. 109-120.
@article{4787fc3ae4f243808835eab2a94c3dd2,
title = "Real option in action: An example of flexible decision making at a mine operational level",
abstract = "Flexibility and operational adaptability are essential for long term corporate success and real option (RO) appears suitable for analysing risky projects. Nevertheless, its application in engineering design has been slow-moving compared to financial uses. Therefore, there is a compelling argument for using visual, intuitive and transparent models, such as the binomial decision tree, which has the potential to eliminate decision maker apprehension and improve RO use in engineering design and decision making. This paper reviews RO applications in mining projects and proposes a new methodology to explore technical applications of RO in mine design and decision making at the mine operational level. The research will investigate the suitability of using the RO method at the mine operational level where production decisions are made frequently, rather than organisational strategies that are reviewed after several years. The proposed approach is applied to a case study. This will demonstrate how RO can be used in designing multiple pits in multi-zone ore deposits to create a switching option between pits regarding changing ore grades and fluctuating commodity prices. The main rationale of this option involves deferring waste materials by switching mining activities from a high to low strip ratio pit. This creates a choice between using new RO thinking and the traditional methodology. The option is analysed using the binomial decision tree. The results summarised in this paper's conclusion reveal that the project's value increased considerably when flexibility was included in the mine design. These increases in project value were between eight to 15 per cent, depending on the number of flexible options incorporated into the design.",
keywords = "Application of real option at mine operational level, Binomial model, Decision making, Flexible design, Risk, Switching option between pits, Uncertainty",
author = "Ajak, {Ajak Duany} and Erkan Topal",
year = "2015",
doi = "10.1016/j.resourpol.2015.04.001",
language = "English",
volume = "45",
pages = "109--120",
journal = "Resources Policy",
issn = "0301-4207",
publisher = "Elsevier",

}

TY - JOUR

T1 - Real option in action

T2 - An example of flexible decision making at a mine operational level

AU - Ajak, Ajak Duany

AU - Topal, Erkan

PY - 2015

Y1 - 2015

N2 - Flexibility and operational adaptability are essential for long term corporate success and real option (RO) appears suitable for analysing risky projects. Nevertheless, its application in engineering design has been slow-moving compared to financial uses. Therefore, there is a compelling argument for using visual, intuitive and transparent models, such as the binomial decision tree, which has the potential to eliminate decision maker apprehension and improve RO use in engineering design and decision making. This paper reviews RO applications in mining projects and proposes a new methodology to explore technical applications of RO in mine design and decision making at the mine operational level. The research will investigate the suitability of using the RO method at the mine operational level where production decisions are made frequently, rather than organisational strategies that are reviewed after several years. The proposed approach is applied to a case study. This will demonstrate how RO can be used in designing multiple pits in multi-zone ore deposits to create a switching option between pits regarding changing ore grades and fluctuating commodity prices. The main rationale of this option involves deferring waste materials by switching mining activities from a high to low strip ratio pit. This creates a choice between using new RO thinking and the traditional methodology. The option is analysed using the binomial decision tree. The results summarised in this paper's conclusion reveal that the project's value increased considerably when flexibility was included in the mine design. These increases in project value were between eight to 15 per cent, depending on the number of flexible options incorporated into the design.

AB - Flexibility and operational adaptability are essential for long term corporate success and real option (RO) appears suitable for analysing risky projects. Nevertheless, its application in engineering design has been slow-moving compared to financial uses. Therefore, there is a compelling argument for using visual, intuitive and transparent models, such as the binomial decision tree, which has the potential to eliminate decision maker apprehension and improve RO use in engineering design and decision making. This paper reviews RO applications in mining projects and proposes a new methodology to explore technical applications of RO in mine design and decision making at the mine operational level. The research will investigate the suitability of using the RO method at the mine operational level where production decisions are made frequently, rather than organisational strategies that are reviewed after several years. The proposed approach is applied to a case study. This will demonstrate how RO can be used in designing multiple pits in multi-zone ore deposits to create a switching option between pits regarding changing ore grades and fluctuating commodity prices. The main rationale of this option involves deferring waste materials by switching mining activities from a high to low strip ratio pit. This creates a choice between using new RO thinking and the traditional methodology. The option is analysed using the binomial decision tree. The results summarised in this paper's conclusion reveal that the project's value increased considerably when flexibility was included in the mine design. These increases in project value were between eight to 15 per cent, depending on the number of flexible options incorporated into the design.

KW - Application of real option at mine operational level

KW - Binomial model

KW - Decision making

KW - Flexible design

KW - Risk

KW - Switching option between pits

KW - Uncertainty

UR - http://www.scopus.com/inward/record.url?scp=84934893591&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84934893591&partnerID=8YFLogxK

U2 - 10.1016/j.resourpol.2015.04.001

DO - 10.1016/j.resourpol.2015.04.001

M3 - Article

VL - 45

SP - 109

EP - 120

JO - Resources Policy

JF - Resources Policy

SN - 0301-4207

ER -